    • Idea conceiving in Dec 17 to dev integrated Pakistan’s first Championship Signature Golf..
    • Eric Els sel for design and consultancy but later regretted.

  • March
    • Meeting held with SNF team for designing of RGC.
  • June
    • Contract agreement signed with “FDI” for design.
  • July
    • Desert Group was engaged on recom of FDI through Channel Architect & Engrs for Proj Mgmt.
  • October
    • James Wood was hired for dev of Real Estate.
  • November
    • Troon Golf and Aqua Turf became part of team for op & mgmt and irrigation design respectively.
    • Gr Breaking ceremony held on 22 Nov
      • COAS (Chief Guest)
      • SNF (Guest of Honor)

  • January
    • Import of used machinery started amongst DHA, Channel Architect, Desert Gp and Jade Machinery.
  • April
    • Direct contract was executed b/w DHA & Desert Gp leaving Channel Architect and Engrs.
  • May
    • Desert Gp and contractor (M/S 4M) mob to start works of RGC
  • October
    • Golf const machinery arrived
    • Const commenced

  • March
    • M/S Usman Engr took over the site from main golf course contractor (M/s 4 M) for Earthworks and allied works
  • March & April
    • Work remained suspended.
  • Dev took place in two stages:-
    • Back Nine
    • Front Nine

  • Golf Course completed in May in 18 months record time.